OtherPapers.com - Other Term Papers and Free Essays
Search

Fauquier Gas Company

Essay by   •  April 9, 2012  •  Case Study  •  457 Words (2 Pages)  •  3,654 Views

Essay Preview: Fauquier Gas Company

Report this essay
Page 1 of 2

FAUQUIER GAS COMPANY

MAJOR FACTS

I. 3 ½ miles of gas lines need to be laid by September.

II. The supply organization was under the management control of the vice president for operations.

III. Mr. Charlie Buck the design superintendent headed the design organization. Both the design and construction organizations were under the management control of the vice president of operations.

IV. Mr. Bill Murphy is the supply manager, M. Charlie Buck is the design superintendent, and Mr. Pat Wilson is the design engineer.

MAJOR PROBLEM

Mr. Murphy prior purchases for pipe was 3/8 inch thick and 40 feet in length and the new specification would be 24 inches and a wall thickness of ¾ of an inch and 57 feet long. Mr. Murphy would not have known this if he had not over heard it at lunch on April 14th.

POSSIBLE SOLUTION

A. Mr. Murphy needs t request a meeting with all the parties, Mr. buck the design superintendent, Mr. Wilson the design engineer and the vice president of operations. The meeting should be held in regards to the upcoming project to discuss the specifications of the pipe and the timeline to meet the project deadline.

CHOICE AND RATIONALE

A. I think a meeting of all 4 individuals involved should be held to discuss the project to ensure that Mr. Murphy can get the ball rolling on the right size of pipe, because if Mr. Murphy had not overheard the conversation about the ongoing project he would have order the wrong size pipe and the project would not have the deadline. The lack of communication has already put the project's potential completion date back.

IMPLEMENTATION

Mr. Murphy needs to schedule a meeting with the vice president of operations. Mr. Murphy needs to explain that currently, there is no relationship that consists between construction and supply management. That they failed to notify his department of their findings and specifications changes. Mr. Murphy needs to request that a meeting take place between Charlie Buck, Pat Wilson and Sam Law to explain the fundamental importance of open communication and his involvement with changes to supplies and specifications. During their first meeting Mr. Murphy needs to explain that any supplies and specifications needs to be brought to his attention as soon as they are made aware of it, because he needs to allow for time to order the supplies needed for construction to complete the project.. In order for this implementation to be a success he needs to have the backing of the vice president of operations; therefore it is

...

...

Download as:   txt (2.6 Kb)   pdf (61.3 Kb)   docx (9.5 Kb)  
Continue for 1 more page »
Only available on OtherPapers.com