Financial Plan Assignment
Essay by people • August 19, 2012 • Coursework • 799 Words (4 Pages) • 1,618 Views
Financial Plan Assignment
1.
Material:
1. Equipment A: $ 15,000
Equipment B: $ 35,000
2. Material required for electrical hook-up (400 *25) : $10000
3. Controls 600*2: $ 1200
4. Required start-up material 3700*2.70 : $ 9990
Total Material $71190
Labor:
5. Company labor for installation (2*16*35): $ 1120
6. Contract labor: $ 7,500
Total Labor $ 8620
Overhead:
7. Engineering (71190*0.15): $10678.5
8. Inspection (8620*0.03): $258.6
9. General and Administrative (71190+8620)*0.05: $3990.5
Total overhead $ 14604.60
Total project cost = $94,737.60
2.
a) Pexp = (Popt + 4 x Pmost + Ppess) / 6
Pexp = (0.24 + (4 x 0.30) + 0.62) / 6
Pexp = $0.34/lb
(b) Expected Amount
Pexp = (Popt + 4 x Pmost + Ppess) / 6
Pexp = (37 + (4 x 40) + 49) / 6 = 41 tons.
c) The expected cost for structural steel over the life of the project
$0.34* (41*2000) lbs.= 27880 lbs.
d) The expected cost for structural steel over the life of the project
Expected cost:
$10.17/lb. x 5,170 lbs. = $52,578.90
Most optimistic cost:
$0.24* (37*2000) lbs. =$ 17760
Most pessimistic cost:
$0.62*(49*2000) lbs. =$ 60760
The final estimated cost for the material is:
($17760 + (4 x $27880) + $60760)) / 6 = $31673
...
...