Method Statement for False Ceiling Works
Essay by Abhishek Jain • April 11, 2017 • Study Guide • 1,754 Words (8 Pages) • 1,699 Views
METHOD STATEMENT FOR FALSE CEILING (GYPSUM BOARD&GRG CEILING) WORK
| ||||||||||||||||||||||||||||||||||||
1.0 | Method Statement for FALSE CEILING works: | |||||||||||||||||||||||||||||||||||
2.0 | Scope: To scope of this method statement covers entire false ceiling works for the entire project It includes
| |||||||||||||||||||||||||||||||||||
3.0 4.0 | References: General Specifications Vol.2A.2 of contract documents (Page no-R/40 to R /45) Contract drawings / Approved Shop drawings Approved Materials – As per Material submittal Approved Project Safety plan and Procedures( Ref no DSC/04-340/MRVC2/RD/87 – dated 7/11/2007) Testing Schedule: It should be ensured that the necessary tests being carried out as per the attached ITP | |||||||||||||||||||||||||||||||||||
5.0 | Access: A safe and a proper access to the site of works is to be provided so that, men and materials, plant and machinery along with tools & tackles can easily reach the site of works. Only authorized person from main contractor and (or) sub contractor should enter the site with proper PPE and tools and equipments. | |||||||||||||||||||||||||||||||||||
6.0 | Working hours: False ceiling works shall be carried out during day time i.e. 8:00 am to 6:00 pm from December to February and & 7:00 am to 7:00 pm during March to November with the exception of 12:00 am to 3:00 pm during July to August. In case false ceiling works has to be carried out during night time it shall be done with due permission from the consultant. | |||||||||||||||||||||||||||||||||||
7.0 | Lighting/ Safety Lighting: Proper lighting should be arranged in case the work is continuing night time. All mechanical equipment/ vehicles etc. should be arranged with glowing safety light to Engineer’s satisfaction. | |||||||||||||||||||||||||||||||||||
8.0 | Plant & Equipment Schedule:-
| |||||||||||||||||||||||||||||||||||
9.0 | Personal Protective Equipment: Every workman or supervisor shall be wearing the following PPE
| |||||||||||||||||||||||||||||||||||
10.0 | Power Electricity power is required for waterproofing works. | |||||||||||||||||||||||||||||||||||
11.0 | Materials:
LT-EST/DIAR/MAT/456,457 Dated 9/9/2008
LT-EST/DIAR/MAT/463, Dated 24/7/2008
| |||||||||||||||||||||||||||||||||||
12.0 | Method of work:[pic 1] [pic 2] [pic 3] [pic 4] [pic 5] [pic 6] [pic 7] [pic 8] [pic 9][pic 10] [pic 11] [pic 12] [pic 13] [pic 14] [pic 15][pic 16] [pic 17] [pic 18] [pic 19] [pic 20] [pic 21] [pic 22] [pic 23] | |||||||||||||||||||||||||||||||||||
13.0 14.00 | Detailed Working Methodology for GYPSUM PLASTER BOARD CEILINGS 13.10 FIXING OF 12.5mm THICK GYPSUM PLASTER BOARD CEILINGS, BULKHEADS AND BORDERS a) Fixing of gypsum plaster board, ceilings and bulkhead will be carried out in stages listed below
13.20 Site survey:- Before commencement of the work site survey will be made with the Site engineer to check the following works
Before starting of the first fix services of false ceiling clearance will be obtained from the consultant and M.E.P sub contractor as the first fix services of M.E.P above the false ceiling to be completed and approved 13.30 First fix:-
Before starting of the second fix services of false ceiling clearance will be obtained from the contractor, consultant and M.E.P sub contractor for the second fix services of M.E.P above the false ceiling to be completed and approved as well as inspection of the structural frame of false ceilings should be carried out by the consultant and should be rectified to the comments if any given by them 13.40 Second fix:-
Before starting of the third fix services of false ceiling marking will be made by M.E.P sub contractor for the third fix services such as all the electrical points, A/C supply and return air diffuser position, sprinkler points and position of access panel as per approved coordinated drawings and inspection by the consultant and contractor to be obtained for final approval of cutting. 13.50 Third fix:-
Detailed Working Methodology for “GRG” CEILING 14.10 FIXING OF 600x600mm “GRG” CEILING Fixing of 600x600mm ceilings will be carried out in stages listed below
14.20 Site survey:- Before commencement of the work site survey will be made with the contractor to check the following works
Before starting of the first fix services of false ceiling clearance will be obtained from the consultant and M.E.P sub contractor as the first fix services of M.E.P above the false ceiling to be completed and approved 14.30 First fix:-
Before starting of the second fix services of false ceiling clearance will be obtained from the consultant and M.E.P sub contractor for the second fix services of M.E.P above the false ceiling to be completed and approved as well as inspection of the suspension frame of false ceilings should be carried out by the consultant and should be rectified to the comments if any given by them. 14.40 Second fix:-
| |||||||||||||||||||||||||||||||||||
15.0 16.0 17.0 18.0 19.0 | Quality Control Measures & Responsibilities L&TE-JV shall maintain the completed inspection of Test plans and inspection reports as quality records. L&T EST-JV engineer will be responsible for quality control at the site. CM/Project Engineer/QA/QC Engineer/site engineer and their team will carry out surveillance checks and will maintain original copies of all tests and record on file. Before the commencement of work QA/QC will check as per approved check list and Site Engineer will be hand over to the respective consultant engineers. Safety, Health & Environmental Issues. All work shall be carried out as per the project ES&H plan. Proper sign shall be provided and constant check by the safety engineer shall be implemented. All the appropriate personal should wear proper PPE which must include overalls, good quality gloves, goggles and face mask. General health and safety requirement for every particular project shall be fully adhered by all site personnel. In particular full body harness is to be used by all operatives while carrying outworks on Scaffolding. Also safety masks are to be used for application of sealants and grouts. Service Shut Down - Not required. Emergency arrangement, communication:- Every precaution should be arranged to avoid any accident or injury. One safety officer will always be available to give proper direction and to make safety working atmosphere The site office shall be equipped with first aid facility and one male nurse is also available in case of emergency, the injured person should immediately shifted and proper first aid shall be Provided, & shall arrange medical facility in any hospital which near to site office, if required. Fire Precaution Approved fire extinguisher shall be made available at prominent locations as per ES & H plan. Necessary training shall be provided to the labor in operation of fire extinguisher in proper manner as per the ES & H plan. | |||||||||||||||||||||||||||||||||||
...
...