Essay by people • July 17, 2011 • Study Guide • 287 Words (2 Pages) • 4,886 Views
MG375 July 7, 2011
a. Draw a project network that includes all the activities.
a. Calculate the start and finish times for each activity and determine the minimum number of weeks for completing the project.
Product Specifications 7 Weeks (5 weeks plus additional 2 for P4)
Supplier Specifications 6 Weeks
Product Design 12 Weeks (8 weeks plus additional 4 for D5)
Product Integrations 10 Weeks (5 weeks plus an additioanl 5 for 13)
Subcontracting 12 Weeks
Find the Critical set of activities for the project.
P1, P2, S1, D2, 11, 13, V2 = 25 Weeks
P1, P2, S1, D3, 11, 13, V2 = 26 Weeks
P1, P2, S1, D4, 11, 13, V2 = 28 Weeks
P1, P2, S1, D1, 11, 13, V2 = 32 Weeks
P1, P2, S1, S3, D6, 11, 13, V2 = 32 Weeks
P1, P2, S1, S3, D6, D7, 12, 13, V2 = 32 Weeks
P1, P2, S1, S3, D6, D7, V1,
...
...