OtherPapers.com - Other Term Papers and Free Essays
Search

Woody 2000 Project Squence of Activities

Essay by   •  February 17, 2017  •  Coursework  •  930 Words (4 Pages)  •  1,122 Views

Essay Preview: Woody 2000 Project Squence of Activities

Report this essay
Page 1 of 4

Woody 2000        Landscape        11-Dec-13 12:31[pic 1][pic 2]

A1260

Project Start Date

0

01-Jan-14

0

$0.00

Project Start Date

A1270

Design Start

0

08-Jan-14

0

$0.00

Design Start

A1280

Design Finish

0

18-Feb-14

0

$0.00

Design Finish

A1290

Shop drawings Start

0

19-Feb-14

0

$0.00

Shop drawings Start

A1330        Construction Start        0        19-Mar-14        0        $0.00        Construction Start

A1310

Materials Delivery start

0

02-Apr-14

0

$0.00

Materials Delivery start

A1300

Shop drawings finish

0

08-Apr-14

0

$0.00

Shop drawings finish

A1320

Materials Delivery Finish

0

19-Aug-14

0

$0.00

Materials Delivery Finish

A1350

Closeout Start

0

20-May-15

0

$0.00

Closeout Start

A1340        Construction Finish        0        09-Jun-15        0        $0.00

A1360        Project Finish        0        30-Jun-15        0        $0.00

Design Phase        30        08-Jan-14        18-Feb-14        30        $600,000.00[pic 3]

A1000        Project Design        30        08-Jan-14        18-Feb-14      Design Office, Cost        30        $600,000.00

Engineering        130        19-Feb-14        19-Aug-14        300        $7,250,000.00[pic 4][pic 5][pic 6][pic 7][pic 8]


  1. Feb-14, Design Phase Project Design

  1. Aug-14, Engineering

Construction Finish

Project Finish

Materials

130

19-Feb-14

19-Aug-14

250

$7,225,000.00

19-Aug-14, Materials

A1030

Materials submittal        25

19-Feb-14

25-Mar-14

Contractor, Cost        25

$15,000.00

Materials submittal

A1040

Materials Approval        25

05-Mar-14

08-Apr-14

Design Office, Cost        25

$10,000.00

Materials Approval

A1050

Materials Procurement        100

19-Mar-14

05-Aug-14

Contractor, Cost        100

$7,000,000.00

Materials Procurement

A1060

Materials Delivery        100

02-Apr-14

19-Aug-14

Contractor, Cost        100

$200,000.00

Materials Delivery

Construction Phase        320

19-Mar-14

09-Jun-15

7950

$9,030,000.00

09-Jun-15, Construction P

Extention of existing floor area        320

19-Mar-14

09-Jun-15

5050

$6,680,000.00

09-Jun-15, Extention of ex

Substructure

135

19-Mar-14

23-Sep-14

1350

$1,830,000.00        23-Sep-14,  Substructure

A1070

Excavation Works

40

19-Mar-14

13-May-14

resources, Cost

200

$300,000.00        Excavation Works

A1080

P.C Concrete

25

14-May-14

17-Jun-14

resources, Cost

200

$200,000.00        P.C Concrete

A1090

R.C concrete

30

11-Jun-14

22-Jul-14

resources, Cost

300

$1,000,000.00        R.C concrete

A1100

Waterproofing

15

23-Jul-14

12-Aug-14

resources, Cost

150

$80,000.00        Waterproofing

A1110

Backfilling

30

06-Aug-14

16-Sep-14

resources, Cost

400

$100,000.00        Backfilling

A1120

Slab On Grade

10

10-Sep-14

23-Sep-14

resources, Cost

100

$150,000.00        Slab On Grade

Superstructure

90

24-Sep-14

27-Jan-15

1350

$1,000,000.00        27-Jan-15, Superstructure

A1130

Columns Works

40

24-Sep-14

18-Nov-14

resources, Cost

600

$200,000.00        Columns Works

A1140

Slabs Works

50

19-Nov-14

27-Jan-15

resources, Cost

750

$800,000.00        Slabs Works

...

...

Download as:   txt (8.3 Kb)   pdf (363.6 Kb)   docx (405.1 Kb)  
Continue for 3 more pages »
Only available on OtherPapers.com