A: Requirement for preparation of Factory Plan:-
All reference drawings required with one Hard Copy & Soft Copy
1) Site Plan / General layout with North direction.
2) Key plan which include 5 km area from the site circumference.
3) Individual plan view of building / structure which include machinery layout (Name & size of equipment / machinery) with floor wise (level wise) detail.
4) Longitudinal & Latitudinal cross section of building / structure with clear height.
5) Elevation of Individual building / structure.
6) Drawing of fire hydrant network in general layout.
B: Requirement of documents for submission of factory plan:-
1) Name & site address of company.
2) NOC from Local Authority for construction permission (one photocopy)
3) Land proof (ownership proof) (one photocopy)
4) Name of Occupier with present address.
5) Forwarding letter for submission of plan (on letter head in duplicate)
6) Employees strength (shift-wise) (male-female) existing & proposed.
7) Flow process chart / diagram (in triplicate)
8) List of raw materials with quantity (in triplicate)
9) List of finish product (in triplicate)
10) Manufacturing process (write up) (in triplicate)
11) Detail of fire extinguishers to be provided like capacity, quantity, type & location (in triplicate).
12) Gujarat Pollution Control Board, NOC / Consent (if applicable). (one photo copy).
13) List of chemicals which will be used in process or supporting to process (if any) with max. storage quantity (in triplicate).
14) Material Safety Data Sheet of chemicals (if any). (in triplicate).
15) Schedule-7, Annexure-4 & 6 (if required) (in triplicate)
16) Photocopy of Last Approved plan.
17) Photocopy of Factory Licence.
18) Cess challan under Building & Other Construction Act.