Workload Scheduling
Essay by ssmith99 • July 27, 2012 • Essay • 574 Words (3 Pages) • 1,120 Views
1.
a) Define the decision variables.
Oi = number of one month contract employees hired (where i = 1, 2, 3, 4, 5, 6 for January, February, March, April, May, June)
Wi = number of two month contract employees hired (where i = 1, 2, 3, 4, 5 for January, February, March, April, May)
Hi = number of three month contract employees hired (where i = 1, 2, 3, 4 for January, February, March, April)
b) Define the objective function
Min. total wage costs for contract employees (cost per contract length) x (number of contracts of each length used)
Min. 2,875*Oi + 5,675*Wi + 8,375*Hi
c) Define the constraints
O1 + W1 + H1 >= 10
W1 + H1 + O2 + W2 + H2 >= 23
H1 + W2 + H2 + O3 + W3 + H3 >= 19
H2 + W3 + H3 + O4 + W4 + H4 >= 26
H3 + W4 + H4 + 05 + W5 >= 20
H4 + W5 + O6 >= 14
Oi, Wi, Hi >= 0
Oi, Wi, Hi must be an integer
d) Determine the optimal solutions:
Jan. Feb. Mar. Apr. May. June.
Option 1 0 4 0 0 3 0
Option 2 0 0 0 3 0 0
Option 3 10 9 0 14 0 0
2.
Number Hired Contract Cost Training Cost Total Cost
Option 1 7 $14,000 $6,125 $20,125
Option 2 3 $14,400 $2,625 $17,025
Option 3 33 $247,500 $28,875 $276,375
TOTAL 43 $275,900 $37,625 $313,525
Total Cost = $313,525
3.
a) Schedule for temporary employees and Costs:
Jan. Feb. Mar. Apr. May. June.
Option 1 10 23 19 26 20 14
Option 2 0 0 0 0 0 0
Option 3 0 0 0 0 0 0
Number Hired Contract Cost Training Cost Total Cost
Option 1 112 $224,000 $78,400 $302,400
Option 2 0 $0 $0 $0
Option
...
...